search
cart
facebook instagram twitter linkedin youtube
  • Sign In
  • Create Account
  • Sign Out
  • My Account
  • NEWS
  • PRODUCTS
    • FEATURED PRODUCTS
  • CONTRACTORS
    • BATH & KITCHEN PRO
    • BUSINESS MANAGEMENT
    • HIGH EFFICIENCY HOMES
    • TECHNOLOGY
    • WATER TREATMENT
    • PMC COLUMNS
      • Dave Yates: Contractor’s Corner
      • John Siegenthaler: Hydronics Workshop
      • Kenny Chapman: The Blue Collar Coach
      • Matt Michel: Service Plumbing Pros
      • Scott Secor: Heating Perceptions
  • ENGINEERS
    • CONTINUING EDUCATION
    • DECARBONIZATION | ELECTRIFICATION
    • FIRE PROTECTION
    • GEOTHERMAL | SOLAR THERMAL
    • PIPING | PLUMBING | PVF
    • PME COLUMNS
      • Christoph Lohr: Strategic Plumbing Insights
      • David Dexter: Plumbing Talking Points
      • James Dipping: Engineer Viewpoints
      • John Seigenthaler: Renewable Heating Design
      • Lowell Manalo: Plumbing Essentials
      • Misty Guard: Guard on Compliance
  • RADIANT & HYDRONICS
    • RADIANT COMFORT REPORT
    • THE GLITCH & THE FIX
  • INSIGHTS
    • CODES
    • GREEN PLUMBING & MECHANICAL
    • PROJECT PROFILES
    • COLUMNS
      • Codes Corner
      • Natalie Forster: Editorial Opinion
      • Guest Editorial
  • MEDIA
    • EBOOKS
    • PODCASTS
    • VIDEOS
    • WEBINARS
  • RESOURCES
    • INDUSTRY CALENDAR
    • DIRECTORIES
    • PM BOOKSTORE
    • CE CENTER
    • MARKET RESEARCH
    • CLASSIFIEDS
  • EMAGAZINE
    • EMAGAZINE
    • ARCHIVE ISSUES
    • CONTACT
    • ADVERTISE
    • PME EMAGAZINE ARCHIVES
  • SIGN UP!
ColumnsRadiant & HydronicsThe Glitch & The Fix

The Glitch & The Fix: February 2025

A heat pump heat migration problem

By John Siegenthaler, P.E.
Figure 1 glitch drawing for February 2025

Image courtesy of John Siegenthaler

February 28, 2025
✕
Image in modal.

The Glitch

A heating contractor is asked to install two identical air-to-water heat pumps to take over as the primary hydronic heat source for a large home. Each heat pump has its own internal circulator. The existing boiler will be retained as the supplemental and backup heat source. A standard multi-boiler staging controller will be used to operate the heat pumps as rotating stages 1 and 2, and the boiler as “fixed” stage 3. These heat sources will supply several zones of low-temperature thin-slab radiant floor heating.

The existing system uses a 1.5” pipe size thermostatic mixing valve to reduce the water temperature from the boiler to the floor circuits.

After the heat pumps are added, there’s noticeable heat migration into zones that are supposed to be off. The galvanized vent connector from the boiler to the chimney also has to be periodically replaced due to corrosion.

The system — as installed — is shown in Figure 1. The piping layout was meant to salvage as much of the original installation as possible. Can you identify some problems with this design and suggest modifications that would correct them?

FIGURE 1

Figure 1 glitch drawing for February 2025

Image courtesy of John Siegenthaler

The Gitches

  1. Although each heat pump has its own circulator, each heat pump doesn’t have its own check valve. When one heat pump circulator is on and the other is off, some of the flow from the active heat pump circulator will pass in reverse through the inactive heat pump. This reduces flow to the buffer tank and increases the entering water temperature to the active heat pump. 
  2. Another issue is created by circulator (P1) in Figure 1. When operating this circulator is partially in series with the zone circulators. The differential pressure it creates is sufficient to push heated water through the check valves in the inactive zone circulators, which is the underlying cause of the heat migration. 
  3. The corrosion of the vent connector pipe is due to a lack of anti-condensation protection for the oil-fired boiler. As built, low-temperature water returning from the radiant floor circuits goes directly into the boiler. That water holds the temperature on the combustion side of the boiler’s heat exchanger below the dewpoint of the exhaust gases causing them to condense into an acidic liquid. From the standpoint of chemistry, a galvanized steel vent pipe is no match for that liquid. Holes through the pipe can form in a few months.
  4. Adding a buffer tank to the system significantly increases the system’s volume. The existing expansion tank should be checked to see if it is large enough to accommodate the total expansion volume of the modified system. A 2-gallon tank is not large enough. Converting the system from water to a mixture of propylene glycol further exacerbates the issue since antifreeze solutions have a higher volumetric expansion rate relative to water. It’s likely that this system should have a nominal 7-gallon (or larger) expansion tank.
  5. The thermostatic mixing valve may have worked when the boiler was the sole heat source, but it’s not needed after the heat pumps take over as the primary heat source. There is no point in operating the heat pumps at leaving water temperatures higher than currently required by the space heating load, and then mixing that temperature down. The temperature of the buffer tank should be maintained based on outdoor reset control and the thermostatic mixing valve eliminated.
  6. Since there are valves for isolating either heat pump during service, there should also be a pressure relief valve between those valves and the heat pump. It needs to be there to protect against over-pressure in the unlikely (but possible) event that the heat pump was turned on while isolated from the remainder of the system.

The Fixes

Figure 2 shows one way to modify the system to correct all of the above issues with minimal disruption of existing piping and components.

FIGURE 2

Figure 2 fix drawing for February 2025

Image courtesy of John Siegenthaler

Check valves have been added to the outlet connection on each heat pump to prevent flow reversal when only one heat pump is operating.

Existing circulator (P1) is now regulated by a variable speed injection mixing controller that monitors the supply temperature to the zone circuits and “injects” heated water from the buffer tank as necessary to maintain a target supply water temperature to the zones. This eliminates the need for the thermostatic mixing valve.

Although it would be possible to just operate circulator (P1) at a fixed speed doing so could lead to “over pumping” when the total flow rate of all active zones is less than the flow through (P1). The result would be heated water returning to the lower portion of the buffer tank and disrupting beneficial temperature stratification within the tank. If the total flow rate of all active zones was higher than the flow through (P1) (e.g., “under pumping”) some of the flow returning from the zones would pass through the closely spaced tees, mix with the heated water from the buffer tank and reduce the supply temperature to the active zone. Both of these scenarios are prevented by supply temperature feedback to the injection mixing controller.

A pair of closely spaced tees creates the necessary hydraulic separation between circulator (P1) and the zone circulators, eliminating the previous heat migration into inactive zone circuits.

The boiler is also interfaced to the zone distribution system using a second injection mixing circulator. That controller monitors the supply water temperature whenever the boiler is operating (which should be infrequently now that two heat pumps are in the system as primary heat sources). The speed of the circulator is adjusted to maintain a target supply water temperatures based on outdoor reset. The injection controller also monitors the boiler inlet temperature and limits heat transfer away from the boiler as necessary to prevent sustained flue gas condensation. The injection piping interfaces to the zone distribution system through another set of closely spaced tees, which provide hydraulic separation between the injection circulator and the zone circulators.

Additional thoughts 

Because the new heat pumps have variable speed compressors, they have a nominal 3:1 turndown ratio. Since there are two identical heat pumps the turndown ratio of the heat pump “plant” is 6:1. Given this wide range of capacity control and the relatively high thermal mass of the floor heating system, a hydraulic separator could have been used instead of the buffer tank. This would definitely reduce cost, reduce space requirements in the mechanical room, and displace the need for air and dirt separators elsewhere in the system.

In this scenario the heat pumps would need to have 0-10 VDC input for compressor speed control. The system would be operated by a controller that could stage and modulate the output of each heat pump. A 3-stage controller with a 0-10VDC output to each heat pump, combined with a third on/off output for the boiler would work. Such controllers are currently available.

A thermostatic anti-condensation valve would be used to protect the boiler.

A schematic for this scenario is shown in Figure 3.

FIGURE 3

Figure 3 alternative fix drawing for February 2025

Image courtesy of John Siegenthaler

Are you an ace troubleshooter?

PM’s Hydronics Editor John Siegenthaler, P.E., will pose a question to you, our readers, to review a system’s schematic layout and discover its faults, flaws and defects. Good luck!
Read More The Glitch & The Fix⮞

KEYWORDS: air-to-water heat pumps heat pumps hydronic heat

Share This Story

Looking for a reprint of this article?
From high-res PDFs to custom plaques, order your copy today!

John siegenthaler 200x200

John Siegenthaler, P.E., is a consulting engineer and principal of Appropriate Designs in Holland Patent, New York. In partnership with HeatSpring, he has developed several online courses that provide in-depth, design-level training in modern hydronics systems, air-to-water heat pumps and biomass boiler systems. Additional information and resources for hydronic system design are available on Siegenthaler’s website,  www.hydronicpros.com.

Recommended Content

JOIN TODAY
to unlock your recommendations.

Already have an account? Sign In

  • 2025 Next Gen ALL-STARS hero 1440

    2025 Next Gen All Stars: Top 20 Under 40 Plumbing Professionals

    This year’s group of NextGen All-Stars is full of young...
    Plumbing & Mechanical Contractor
    By: Kristen R. Bayles
  • Worker using the Milwaukee Tool SWITCH PACK drain cleaner

    Pipeline profits: Drain cleaning, pipe inspection create opportunities

    Drain cleaning and inspection services offer lucrative...
    Plumbing News
    By: Nicole Krawcke
  • Uponor employee, Arturo Moreno

    The reinvestment in American manufacturing and training

    Plumbing & Mechanical Chief Editor Nicole Krawcke and...
    Plumbing News
    By: Nicole Krawcke and Natalie Forster
Manage My Account
  • eNewsletters
  • Online Registration
  • Subscription Customer Service
  • eMagazine
  • Manage My Preferences

More Videos

Popular Stories

Hot water pipes

Campus shutdown at Oakland University exposes hidden risks of aging hot-water infrastructure

Floor heating manifold cabinet with flowmeter and PEX pipe.

Elegance extended: How to use the homerun system of connecting heat emitters

Industrial pressure gauge on a tank.

From cutting edge to classic: How to modernize outdated pneumatic control systems

Poll

Will business be up or down in 2025?

Do you anticipate business in 2025 to be up or down in comparison to 2024?
View Results Poll Archive

Products

The Water Came To A Stop

The Water Came To A Stop

See More Products
eBook | 2025 Radiant & Hydronics All Stars

Related Articles

  • The geothermal heat pump is just like a boiler

    See More
  • Integrate a heat pump with a boiler mounted on a brick wall.

    How to integrate a heat pump with a boiler for dual temperature hydronic heating and cooling

    See More
  • A unique air-to-water heat pump system from a business entrepreneur

    See More

Related Products

See More Products
  • 51EpbH0yOwL__SL210_.jpg

    We Got Steam Heat!

  • Lessons Learned in a Boiler Room: A common sense approach to servicing and installing commercial boilers

  • the water book.jpeg

    The Water Came To A Stop

See More Products

Events

View AllSubmit An Event
  • May 29, 2014

    Coffee with Caleffi and John Siegenthaler: Air Source and Water Source Heat Pump Systems.

    Coffee with Caleffi will be hosted by John Siegenthaler on May 29, 2014.
View AllSubmit An Event
×

Keep your content unclogged with our newsletters!

Stay in the know on the latest plumbing & piping industry trends.

JOIN TODAY!
  • RESOURCES
    • Advertise
    • Contact Us
    • Directories
    • Store
    • Want More
    • Supply House Times
  • SIGN UP TODAY
    • Create Account
    • eMagazine
    • eNewsletter
    • Customer Service
    • Manage Preferences
  • SERVICES
    • Marketing Services
    • Reprints
    • Market Research
    • List Rental
    • Survey/Respondent Access
  • STAY CONNECTED
    • LinkedIn
    • Facebook
    • Instagram
    • YouTube
    • X (Twitter)
  • PRIVACY
    • PRIVACY POLICY
    • TERMS & CONDITIONS
    • DO NOT SELL MY PERSONAL INFORMATION
    • PRIVACY REQUEST
    • ACCESSIBILITY

Copyright ©2025. All Rights Reserved BNP Media.

Design, CMS, Hosting & Web Development :: ePublishing