This website requires certain cookies to work and uses other cookies to help you have the best experience. By visiting this website, certain cookies have already been set, which you may delete and block. By closing this message or continuing to use our site, you agree to the use of cookies. Visit our updated privacy and cookie policy to learn more.
This Website Uses Cookies
By closing this message or continuing to use our site, you agree to our cookie policy. Learn More
This website requires certain cookies to work and uses other cookies to help you have the best experience. By visiting this website, certain cookies have already been set, which you may delete and block. By closing this message or continuing to use our site, you agree to the use of cookies. Visit our updated privacy and cookie policy to learn more.
search
cart
facebook twitter linkedin youtube
  • Sign In
  • Create Account
  • Sign Out
  • My Account
  • Home
  • News
  • Columns
    • R&H On The Road
    • John Siegenthaler
    • Dan Holohan
    • Ray Wohlfarth
    • Mark Eatherton: Radiant Know-How
  • Glitch & Fix
  • Products
  • Hydronics
  • Radiant
    • Radiant Comfort Report
  • Buyers Guide
  • Resources
    • Radiant Comfort Report Digital Edition
    • Rep Locator
    • Industry Calendar
    • Store
    • Market Research
    • eNewsletters
  • Plumbing & Mechanical
Home » Radiant floor heat with hydraulic separator needs circulators

You have 0 Articles Left This Month. Register Today for Unlimited Access.

Radiant & HydronicsSolar Thermal/GeothermalThe Glitch & The FixRadiant Heating & Cooling

Radiant floor heat with hydraulic separator needs circulators

The Glitch & The Fix, November 2015

November 10, 2015
John Siegenthaler, P.E.
KEYWORDS floor warming / geothermal systems / incorrect design / radiant system design
Order Reprints
No Comments

An installer is asked to provide a relatively simple single-zone, slab-type floor heating system supplied by a geothermal water-to-water heat pump. He’s heard that a hydraulic separator is a good component in such systems, and designs the layout shown above. He sets the high limit controller for the heat pump at 125° F and the thermostatic mixing valve to 105°.

When the system operates, it only delivers a tiny amount of heat to the building, even when all the circulators are operating. This heat pump only runs for two minutes at a time, then shuts off and locks itself out based on a high pressure fault.

Can you spot several details that are incorrect in the Glitch drawing above, and recommend ways to make the system work as intended?

This system contains many more components than necessary. It also bottlenecks and penalizes the performance potential for the heat pump. Here’s the list of changes.

1. There will be very little circulation on the load side of the hydraulic separator. The circulator supplying the radiant floor circuits may provide adequate flow through those circuits, but that flow is just going to do a U-turn at the closely spaced tees to the right of the hydraulic separator. The only flow that would develop on the right side of this separator will be a tiny momentum-induced flow created by the circulator on the left of the separator.

Don’t blame the hydraulic separator. It’s doing exactly what it is designed to do (e.g., prevent flow in one circuit from inducing flow in a connected circuit). If you’re going to create a circuit and expect more than a trickle of flow through that circuit, it needs to have a circulator.

2. It makes no sense to operate the geothermal heat pump above the temperature necessary to meet the current heating load. Operating the heat pump at 125° F and mixing down the water temperature to the floor circuits just reduces the COP and heating capacity of the heat pump. This scenario also “wastes” the potential of outdoor reset control.

Although the floor might need 105° supply water on a design load day, there are many other days when the water temperature could be lowered and still meet the load. The heat pump should be set up to operate based on outdoor reset control. This will reduce the water temperature in the system under most conditions, and allow the heat pump to operate at the highest possible COP and capacity.

3. It’s not a good idea to install the expansion tank straight down from the bottom connection on the hydraulic separator. Any dirt separated from the flow stream will just land on top of the diaphragm in the tank. Just move the tank connection point to the right of the separator as shown in the Fix drawing above.

4. The piping connections on the heat pump in the Glitch drawing are reversed from what they should be relative to the top-to-bottom flow of refrigerant in the heat pump’s condenser. Always pay attention to the flow direction through the heat exchangers in heat pumps.

5. It’s totally unnecessary to have two circulators on the left side of the hydraulic separator. Just pipe in the heat pump as shown on the Fix drawing, and be sure the circulator can produce the necessary flow and head required by this circuit.

6. It’s good to include a means of readily filling and purging the boiler circuit as well as the distribution system. The purge valve shown in the Fix drawing allow for this. Why spend hours trying to coax bulk air out of the system when you can flush it out in a couple of minutes?

Less parts, lower cost, faster installation, much better performance. Don’t overcomplicate your systems.

You have 0 complimentary articles left.

Register for free today to continue reading!

Already have an account? Sign in here.

Privacy Policy

Related Articles

Hydraulic separator piping to indirect water heater, boilers

Radiant floor heating with pellet boiler

Hydraulic Separator Connections

Geothermal Heat Pump, Mod/Con Boiler For Radiant Floor Heating

RCR logo

RCR Buyers Guide

Plumbing and Mechanical

PM February 2021 Cover

2021 February

The February 2021 issue of Plumbing & Mechanical features how Design & Construction Week Prepares for First ALL-VIRTUAL EVENT, Canadian farmer finds nest egg with fire tube boilers, and much more!

View More Create Account
  • Resources
    • Reprints
    • List Rental
    • Contact Us
    • AEC Store
    • Blogs
    • Radiant & Hydronics
    • Industry Links
    • Market Research
    • Custom Content & Marketing Services
  • Want More
    • Connect
    • Survey And Sample
  • Plumbing Group
    • PM Engineer
    • Supply House Times
  • Advertise
    • Advertise
    • Plan for 2020!
  • Privacy
    • PRIVACY POLICY
    • TERMS & CONDITIONS
    • DO NOT SELL MY PERSONAL INFORMATION
    • PRIVACY REQUEST
    • ACCESSIBILITY

Copyright ©2021. All Rights Reserved BNP Media.

Design, CMS, Hosting & Web Development :: ePublishing